700.7MW Azad Pattan Hydropower Project, AJK/Punjab

Project 700.7MW Azad Pattan Hydropower Project, AJK/Punjab
Primary Energy Input Hydel
Installed Capacity (MW) 700.7
Location Jhelum River
Estimated Cost (US $ Million) 1,600
Executing Company / Sponsors Laraib Energy / China Gezhouba Group Company
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Private Power and Infrastructure Board (PPIB)
Total Jobs Opportunities During the Construction of this Project 3000
Project Progress Update
  • Land Acquisition process started.
  • TPPA, GoP-IA, and GoPb-WUA Signed in July 2020.
  • GoAJK-IA and GoAJK-WUA signed in December 2020.
  • Financial Close (FC) under progress.