1320MW Coal-fired Power Plant at Port Qasim Karachi

Project 1320MW Coal-fired Power Plant at Port Qasim Karachi
Primary Energy Input Coal (Imported)
Technology Super Critical
Installed Capacity (MW) 1320
Location Port Qasim
Province Sindh
Estimated Cost (US $ Million) 1912.2
Executing Company / Sponsors Port Qasim Electric Power Company (Private) Limited
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Private Power and Infrastructure Board (PPIB)
Total Jobs Created 1270
Total Local Jobs Created 960
Total Jobs Created During the Construction of this Project 4000
Project Progress Update
  • Project completed on 25th April 2018.
  • Current Status: Operational

Picture Gallery