300MW Imported Coal Based Power Project at Gwadar, Pakistan

Project 300MW Imported Coal Based Power Project at Gwadar, Pakistan
Primary Energy Input Coal (Imported)
Technology Imported coal
Installed Capacity (MW) 300
Location Gwadar
Province Balochistan
Estimated Cost (US $ Million) 542.32
Executing Company / Sponsors China Communications Construction Company (CCCC)
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Gwadar Port Authority (GPA) / Gwadar Development Authority (GDA)
Project Progress Update
  • LOI was issued on 26th May  2017
  • Site finalized by CCCC
  • Land lease agreement signed by Governenment of Balochistan
  • NOC issued by Balochistan Enviroment Protection Agency (BEPA) on 07-07-2018.
  • Groudbreaking done on 4th November 2019