| Project | 330MW HUBCO ThalNova Thar Coal Power Project |
|---|---|
| Primary Energy Input | Thar Coal |
| Technology | Sub Critical |
| Installed Capacity (MW) | 330 |
| Location | Thar Block - II |
| Province | Sindh |
| Estimated Cost (US $ Million) | 497.70 |
| Executing Company / Sponsors | HUBCO, FFC, China Machinery Engineering Corporation (CMEC) |
| Financing | Independent Power Producer (IPP) |
| Coordinating Ministry | Ministry of Energy (Power Division) |
| Supervising Agency | Private Power and Infrastructure Board (PPIB) |
| Total Jobs Created During the Construction of this Project | 305 |
| Project Progress Update |
|